Project Descriptions

Construction of Potable water lines 1200 , 1500 mm Dia. , from new purification plant station to microwave station, (10th of Ramadan City)

Construction of Potable water lines 1200 , 1500 mm Dia. , the works includes: Prestressed concrete pipe lines of 9 km length & 1500 mm dia. & GRP pipes of 9 km length & 1200 mm dia. - the residential city network pipes Strengthen works of different diameters - washing water treatment disposal works - speedy resolution works with all its contents.

Project Details

Client :New Urban Communities Authority - The Executive Org. for Construction of 10 th of Ramadan City
Activity :Utilities
Location :10th of Ramadan - Cairo Governorate
Finished in :Nov , 2001